TABLE OF CONTENTS

Grid Detection Circuit Installation Overview

Lumin's Grid Detection Circuit (GDC) must be installed in order for Smart Power Mode to function. Until the GDC is energized for the first time, Smart Power Mode will not appear as an available feature in the Lumin mobile app or web portal.

The GDC consists of two AWG #12 wires, one black and one white, that extend out of the flexible conduit that comes pre-installed with the Lumin Smart Panel. These two wires are both labeled GRID. The neutral white wire should be landed on the closest neutral bar to the black wire's point of connection to the site wiring. 


The GDC functions by detecting voltage in a portion of the electrical system that is on the line/utility side of an automatic transfer switch or microgrid interconnection device (e.g., Tesla Gateway). The GDC includes a relay that sends a signal to the Lumin Smart Panel when grid voltage is lost, activating Smart Power Mode. Do not connect the GDC to any portion of the system backed up by batteries or other on-site backup power.


Note that only one GDC is required per installation location. This circuit can be branched off to each Lumin Smart Panel at the location so that they all get the same signal regarding the presence or absence of the grid.


One method of installation is simply to locate a load center that is not backed up by a battery and thus will lose power in the case of an outage. If such a load center is present, the GDC black wire can be landed on its own circuit breaker or pigtailed to an existing circuit where allowed by code. There is virtually no current in the GDC circuit, so it may be connected to any breaker that protects the wire (AWG #12).


When non-backed up circuit breakers are not available, the black wire may also be terminated by tapping non-backed-up feeder conductors that are on the load side of the service disconnect but outside of the Energy Storage System. Ensure proper and code-compliant overcurrent protection is applied when making such a connection.


When no connection can be made on the load side of the service disconnect, the GDC black wire may be connected to a service entrance conductor. Note that this procedure is inherently dangerous and must only be done by qualified personnel. If you are unsure about proper methods for code-compliant supply-side connections for energy management systems, do not proceed.


Grid Detection Circuit Installation Example 

Note: This is an example from the field. Confirm local requirements for supply-side connections and service-rated overcurrent protection/disconnects with your local Authority Having Jurisdiction.


1. Locate a supply-side connection point inside an enclosure.
  • In this example, the line side of a Tesla Gateway I Microgrid Interconnect Device is used. The MID main breaker functions as the service disconnect in this system.
An open enclosure attached to the exterior of a building.
2. The connection to a service entrance conductor is made with an insulated piercing connector (IPC).
  • Follow IPC manufacturer directions, utility directives, and code requirements when making this connection. Many IPCs are not rated for installation on energized wiring. IPCs should always be installed on a straight portion of wire, not along a bend.
A close-up of wires and other components.


The National Electric Code requires that supply-side connections to service wiring use a minimum wire gauge of AWG 6. When connected to the service entrance conductors, this connection must feature a service-rated disconnect so that the GDC can be safely de-energized. It is also necessary to protect the supply-side connected GDC with an overcurrent protection device, which can be integral to the service-rated disconnect or can be a separate device located immediately on the load side of it. A typical approach is to make the connection with a short length of #6 and run that to a service-rated fused disconnect with a fuse appropriately sized to protect the smallest conductors in the GDC. Lumin GDC wiring is 12 AWG and would typically be protected with an OCPD with a rating of no more than 20 amperes. As there should never be any current on the GDC, smaller OCP ratings are acceptable and will not trip/blow under normal conditions.


Only once the GDC is successfully installed will Smart Power Mode become available in the Lumin mobile app and web browser.


GDC Connections on Sol-Ark Systems


In some installations it can be difficult to find a suitable place to land the Grid Detection Circuit. All common Sol-Ark inverters provide a viable option for GDC connection: the inverter's GEN input. This terminal loses voltage during a grid outage and properly activates the GDC if configured correctly in the Sol-Ark settings. This configuration will only work if the GEN input is not being used for any other purpose such as a generator connection.


1. Locate the terminal labeled "L1 GEN" in the Sol-Ark wiring space. Connect the Lumin black wire labeled "Grid Line" to this terminal via an appropriately sized transition wire. 

NOTE: The GEN terminal can accept wire gauges between 2 and 4/0 AWG. The Lumin GDC is 12 AWG. There should never be any current on this circuit; in this application it is being used for voltage sensing only, so 12 AWG is not undersized. However, it is critical to use the specified wire size on the Sol-Ark GEN terminal. A common approach is to use a short length of 2 AWG at the GEN terminal and splice it to the Lumin GDC black wire (12 AWG) using an approved splicing method. The portion of the GDC circuit inside the Lumin Smart Panel contains a 1-A fuse that will protect the smaller-gauge Lumin wiring should it become accidentally energized. 
2. Connect the white Lumin wire labeled "Grid Neutral" to the neutral busbar in the Sol-Ark wiring space. 
3. In the inverter's display menu, open the System Setup Menu by tapping the setup icon:Next, tap on "Battery Setup" then select the Smart Load tab.
4. On the Smart Load screen, select the checkboxes for "AC Coupled Input to Gen" AND "On-Grid always on". All other checkboxes must remain unchecked.
5. Set "Smart Load OFF Batt" to 5% and "Smart Load On Batt" to 0%. 
This configuration will cause the GEN terminals to lose voltage when grid power is lost, activating the Smart Panel's Smart Power Mode. 


GDC Connections on EG4 Systems

18KPV-12LV

In some installations it can be difficult to find a suitable place to land the Grid Detection Circuit. EG4 18KPV-12LV inverters provide a viable option for GDC connection: the inverter's GEN input. When properly configured this terminal loses voltage during a grid outage. This configuration will only work if the GEN input is not being used for any other purpose such as a generator connection.


1. Locate the terminal labeled "L1 GEN" in the Sol-Ark wiring space. Connect the Lumin black wire labeled "Grid Line" to this terminal via an appropriately sized transition wire. 

NOTE: The GEN terminal can accept wire gauges between 2 and 4/0 AWG. The Lumin GDC is 12 AWG. There should never be any current on this circuit; in this application it is being used for voltage sensing only, so 12 AWG is not undersized. However, it is critical to use the specified wire size on the Sol-Ark GEN terminal. A common approach is to use a short length of 2 AWG at the GEN terminal and splice it to the Lumin GDC black wire (12 AWG) using an approved splicing method. The portion of the GDC circuit inside the Lumin Smart Panel contains a 1-A fuse that will protect the smaller-gauge Lumin wiring should it become accidentally energized. 
2. Connect the white Lumin wire labeled "Grid Neutral" to the neutral busbar in the EG4 wiring space. 
3. In the inverter's display menu, open the System Setup Menu by tapping the setup icon:Next, tap on "Battery Setup" then select the Smart Load tab.
4. On the Smart Load screen, select the checkboxes for "AC Coupled Input to Gen" AND "On-Grid always on". All other checkboxes must remain unchecked.
5. Set "Smart Load OFF Batt" to 5% and "Smart Load On Batt" to 0%. 
This configuration will cause the GEN terminals to lose voltage when grid power is lost, activating the Smart Panel's Smart Power Mode. 

GDC Connections with Tesla Backup Switch

The Tesla Backup Switch (BUS) is a Microgrid Interconnect Device (MID) that integrates onsite renewables, battery power, and grid power at the meter base. When a grid outage is detected, the BUS isolates all wiring on the load side of the meter from the utility grid. This simplifies whole-home backup but presents a challenge for energy management systems that need to sense grid presence. In a typical installation the BUS is installed between the meter base and the utility-owned energy meter. The result is that all wiring on the utility side of the BUS belongs to the utility and typically is inaccessible and off-limits for grid detection. All wiring on the load side of the BUS is backed up by the Powerwall batteries and will not de-energize during a grid outage so cannot be used for grid detection. The best solution to this challenge is to install the Tesla BUS in a secondary meter base so that there will be wiring between the utility meter and the BUS that is owned by the homeowner and will be de-energized in a grid outage.  This wiring is suitable for grid detection, either by means of a direct tap of the conductors (overcurrent protection may be necessary) or by use of metering hardware made by Shelly. Note that the Shelly 400 A CTs required for this configuration are fairly large, so this may require a large meter base for the Tesla BUS with space to accommodate the CTs. See the related solutions article for more details about integrating Shelly metering devices: https://luminpanelguard.freshdesk.com/support/solutions/articles/72000650103-remote-grid-detection-with-shelly-meters